Enbridge Energy Line 3 Deactivation Project
Pipe removal will typically follow a sequential process outlined below:survey and staking of construction workspace,vegetation clearing, installation of erosion and sediment control BMPs, and site preparation;excavation and removal of pipe
Project Summary
Location Summary:
approximately 38.1 miles of removal starting at MP 951.8 and ending at MP 989.9
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/2024 (Estimated) |
Comment Period | 04/2025 (Estimated) |
Objection Period Start | 06/2025 (Estimated) |
Decision | 07/2025 (Estimated) |
Implementation | 09/2025 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chippewa National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Developing Proposal
Forests:
Chippewa National Forest
Districts:
Chippewa National Forest All Units
States:
Minnesota
Counties:
Cass; Itasca
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Worthington
200 Ash Avenue NW
Cass Lake, MN 56633
218-335-8643
Christopher.Worthington@usda.gov
Last Updated: 8/28/2024