North Winnie SPNM Forest Plan Amendment
Forest Plan Amendment changing the boundary of the North Winnie Semi-primitive Non-motorized area. Moves south boundary to a road. Develops a trail system and decommissions more unclassified roads.
Project Summary
Location Summary:
North of Lake Winibigoshish. North side of FR 2171 between FR 2382 and 2384.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/28/2008 |
| Comment Period | 02/08/2009 |
| Decision | 06/2009 (Estimated) |
| Implementation | 06/2009 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Blackduck Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Land Management Planning; Special Area Management; Recreation Management
Project Activity:
Plan Amendment; Travel Management
Current Status:
Completed
Project Decision Information
North Winnie SPNM Boundary Change and Trail Project
Decision Signed Date: 06/04/2009
Legal Notice Date: 06/07/2009
Forests:
Chippewa National Forest
Districts:
Blackduck Ranger District
States:
Minnesota
Counties:
Itasca
Legal Land Description:
T147N R28W Sections 13-17 and 20-24
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nancy Salminen
417 Forestry Drive
Blackduck, MN 56630
218-835-3116
nsalminen@fs.fed.us
Last Updated: 6/26/2009