Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/14/2012 |
Comment Period | 05/01/2013 |
Decision | 07/2013 (Estimated) |
Implementation | 11/2013 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chippewa National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Fuels Management; Vegetation Management (Other Than Forest Products); Forest Products
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Blowdown Restoration Project
Decision Signed Date: 07/19/2013
Legal Notice Date: 07/24/2013
Forests:
Chippewa National Forest
Districts:
Chippewa National Forest All Units
States:
Minnesota
Counties:
Beltrami; Cass; Itasca
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sharon Klinkhammer
200 Ash Avenue NW
Cass Lake, MN 56633
218-335-8660
sklinkhammer@fs.fed.us
Last Updated: 7/31/2013