Highway 2 Corridor Improvement Project
Construct 3 passing lanes, several turn lanes, and thin stands on south side of Highway 2 from Cass Lake to Ball Club to improve safety conditions. FS to issue easement along Hwy 2 corridor to MnDOT.
Project Summary
Location Summary:
Highway 2 between Cass Lake and Deer River. Project is within Leech Lake Reservation.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/28/2014 |
| Comment Period | 05/13/2014 |
| Objection Period Start | 06/28/2014 |
| Decision | 08/2014 (Estimated) |
| Implementation | 09/2014 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chippewa National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management; Road Management
Project Activity:
Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Trunk Highway 2 Corridor Improvement Project
Decision Signed Date: 08/25/2014
Forests:
Chippewa National Forest
Districts:
Chippewa National Forest All Units
States:
Minnesota
Counties:
Beltrami; Cass; Itasca
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christine Brown
200 Ash Avenue NW
Cass Lake, MN 56633
218-335-8661
christinembrown@fs.fed.us
Last Updated: 10/18/2019