LLBO Wild Rice Access Improvement
place floating boardwalks across sensitive wetlands in order to provide safe access to important wild ricing areas for LLBO tribal members while reducing wetland damage due to foot and ATV traffic.
Project Summary
Location Summary:
Chub Lake/Mud Lake(MDRNR Lands), Pine Grove -Bowstring River, Bowstring Lake (LLBO Tribal Land), Oak Point Minnesota Island Access.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/20/2021 |
| Decision | 05/2022 (Estimated) |
| Implementation | 06/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (20), 36 Cfr 220.6(E)(20)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Walker Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Heritage Resource Management; Watershed Management
Project Activity:
Trail Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
LLBO Wild Rice Access Improvement
Decision Signed Date: 05/02/2022
Forests:
Chippewa National Forest
Districts:
Walker Ranger District
States:
Minnesota
Counties:
Cass; Itasca
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Todd Tisler
201 Minnesota Ave E.
Walker, MN 56484
907-228-4137
ttisler@fs.fed.us
Last Updated: 6/14/2022