Great River Energy Amendment 15
Rebuilding and maintaining approximately 4.4 miles of transmission line. Replace existing poles with taller poles, heavier conductor wire and shield wire will be utilized to enable monitoring and communication with the electric grid.
Project Summary
Location Summary:
Between Jessie Lake and FR2423
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/16/2022 |
Decision | 09/2022 (Estimated) |
Implementation | 09/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Deer River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Great River Energy Amendment 15
Decision Signed Date: 09/08/2022
Forests:
Chippewa National Forest
Districts:
Deer River Ranger District
States:
Minnesota
Counties:
Itasca
Legal Land Description:
T147N, R25W, Sec. 1, 11, 12; T148N, R25W, Sec. 1, 12, 13, 24, 36; T60N, R27W, Sec. 9, 16, 21
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ashley May klick
1235 Division Street
Deer River, MN 56636
218-229-8807
ashley.n.may-klick@usda.gov