Consumers Energy Electrical Realignment Caberfae/13 Rd
Consumers Energy desires a permit amendment allowing them to realign an existing electrical line to follow a larger, paved road. This will increase the reliability of electrical service for nearby businesses and residents.
Project Summary
Current Status:
Completed
Location Summary:
Along 13 road in Wexford county, Slagle township, T22N R12W, section 24.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/24/2019 |
| Decision | 10/2019 (Estimated) |
| Implementation | 10/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cadillac/Manistee Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Consumers Energy Electrical Realignment Caberfae/13 Rd
Decision Signed Date: 10/08/2019
Forests:
Huron-Manistee National Forest
Districts:
Cadillac/Manistee Ranger District
States:
Michigan
Counties:
Wexford
Legal Land Description:
Wexford county, Slagle township, T22N R12W, section 24.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Katie Racey
1170 Nursery Road
Wellston , MI 49689
231-745-4631 ex 3138
kracey@fs.fed.us
Last Updated: 10/16/2019