Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/07/2015 |
Decision | 11/2015 (Estimated) |
Implementation | 01/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (12), 36 Cfr 220.6(E)(12)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Huron-Manistee National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Vegetation Management (Other Than Forest Products); Forest Products
Project Activity:
Timber Sales (Salvage); Timber Sales (Green)
Current Status:
Completed
Project Decision Information
South Branch Trail Camp CE
Decision Signed Date: 11/30/2015
Forests:
Huron-Manistee National Forest
Districts:
Huron Shores Ranger District
States:
Michigan
Counties:
Iosco
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Elizabeth McNichols
1755 S. Mitchell St.
Cadillac, MI 49601
989-739-0728
emcnichols@fs.fed.us
Last Updated: 11/30/2015