Consumers Energy Powerline Burial
A proposal to amend the Consumers Energy Permit to include about 1800' of additional buried powerline. The line has been requested by a resident surrounded by NFS lands. The line will be buried 36' north of the centerline of FR5483.
Project Summary
Location Summary:
Vicinity of 12 Mile Road in Wexford County, Michigan.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/31/2017 |
Decision | 01/2018 (Estimated) |
Implementation | 05/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cadillac/Manistee Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Consumers Energy Powerline Burial
Decision Signed Date: 01/03/2018
Forests:
Huron-Manistee National Forest
Districts:
Cadillac/Manistee Ranger District
States:
Michigan
Counties:
Wexford
Legal Land Description:
T21N, R12W, Section 31
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jonathan Thompson
1170 Nursery Road
Wellston , MI 49689
231-723-2211
jonthompson@fs.fed.us
Last Updated: 3/21/2018