Wolverine Power Substation Expansions
Amending Wolverine Power's special use permit to authorize the expansion and rebuilding of two existing electrical substations. Rebuilds will respond to increased electric demand and improve reliability. Old equipment to be removed following rebuild.
Project Summary
Location Summary:
Lake County, T17N R12W, Section 19, and Lake County, T17N R13W, Section 3
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/20/2018 |
Decision | 08/2018 (Estimated) |
Implementation | 08/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Baldwin/White Cloud Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Wolverine Power Substation Expansions
Decision Signed Date: 08/06/2018
Forests:
Huron-Manistee National Forest
Districts:
Baldwin/White Cloud Ranger District
States:
Michigan
Counties:
Lake
Legal Land Description:
Lake County, T17N R12W, Section 19, and Lake County, T17N R13W, Section 3
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Katie Racey
650 North Michigan Ave.
Baldwin, MI 49304
231-745-4631 ex 3138
kracey@fs.fed.us