2019 Tippy-Wexford Blowdown Salvage
The purpose of this project is to address blowdown along the ITC Tippy-Wexford transmission corridor. Treatments may include one or more of the following: cutting/felling, topping and leave trees, disposal of slash, and commercial harvest of timber.
Project Summary
Location Summary:
Project area is in Wexford County along 9 miles of ITC electric transmission lines and extends an additional 50 feet to either side of the existing corridor.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/03/2019 |
Decision | 01/2020 (Estimated) |
Implementation | 02/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (13), 36 Cfr 220.6(E)(13)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cadillac/Manistee Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products
Project Activity:
Timber Sales (Salvage)
Current Status:
Completed
Project Decision Information
Salvage of Blowdown in Tippy-Wexford Transmission Corridor
Decision Signed Date: 01/23/2020
Forests:
Huron-Manistee National Forest
Districts:
Cadillac/Manistee Ranger District
States:
Michigan
Counties:
Wexford
Legal Land Description:
T21N, R12W, Sections 9-12; T21N, R11W, Sections 7-11.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jonathan Thompson
1170 Nursery Road
Wellston , MI 49689
231-723-2211
jonthompson@fs.fed.us