Iosco Exploration Trail Project
This project will authorize the construction of 28.3 miles of non-motorized trail as part of the State's Iron Belle Trail System using volunteer and cooperative agreements. This project will also provide connectivity to existing USFS trail systems.
Project Summary
Location Summary:
The US Forest Service segment of the trail somewhat parallels River Road and part of M-65.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/30/2020 |
| Comment Period | 10/13/2021 |
| Objection Period Start | 01/05/2022 |
| Decision | 03/2022 (Estimated) |
| Implementation | 03/2022 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Huron Shores Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Recreation Management; Special Use Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Iosco Exploration Trail Project
Decision Signed Date: 03/07/2022
Forests:
Huron-Manistee National Forest
Districts:
Huron Shores Ranger District
States:
Michigan
Counties:
Iosco
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Andrew Kenyon
5761 N. Skeel Rd
Oscoda, MI 48750
989-826-3252
akenyon02@fs.fed.us
Last Updated: 3/7/2022