Murphy Private Road and Buried Powerline Special Use Permit
This project would issue a special use permit to Mr. Murphy for construction of a 300 foot driveway off a closed route and allow NorthWest Energy to bury an underground residential powerline for 900 feet across NFS to the private building site.
Project Summary
Current Status:
Completed
Location Summary:
Upper Clark Fork Landscape Backyard Butte Management Area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/17/2016 |
| Decision | 08/2016 (Estimated) |
| Implementation | 09/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Beaverhead-Deerlodge National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Murphy Private Road and Buried Powerline Special Use Permit
Decision Signed Date: 08/01/2016
Forests:
Beaverhead-Deerlodge National Forest
Districts:
Butte Ranger District
States:
Montana
Counties:
Silver Bow
Legal Land Description:
T4N, R8W, Sec36
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lucas Phillips
420 Barrett St.
Dillon, MT 59725-3572
208-677-8290
ljphillips@fs.fed.us
Last Updated: 8/9/2016