Montana Interoperable Communications Project - Ellis Peak Communications Site
The BDNF is considering issuing a special use permit for the construction and operation of an Interoperability Montana (IM) communication site on Ellis Peak.
Project Summary
Location Summary:
Ellis Peak in the Tendoy Mountains about 36 miles southwest of Dillon, MT
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/21/2008 |
Comment Period | 12/22/2008 |
Decision | 04/2009 (Estimated) |
Implementation | 06/2009 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Dillon Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Interoperable Montana Communications Project Southwest Loop
Decision Signed Date: 04/21/2009
Legal Notice Date: 04/22/2009
Forests:
Beaverhead-Deerlodge National Forest
Districts:
Dillon Ranger District
States:
Montana
Counties:
Beaverhead
Legal Land Description:
T12S, R12W, Sec. 36
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Reyer Rens
420 Barrett St
Dillon, MT 59725-3573
406-683-3961