Wall Creek / Hyde Creek Pipelines
Construction of two 1.25 inch livestock pipelines and troughs. The Wall Creek Pipeline Extension is .5 miles long off an existing pipeline. Hyde Creek Pipeline extends 0.1 mile from a spring.
Project Summary
Location Summary:
Gravelly Landscape, Wall Creek Management Area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/21/2010 |
| Decision | 06/2012 (Estimated) |
| Implementation | 08/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Madison Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Grazing Management
Project Activity:
Grazing Structural Improvements
Current Status:
Cancelled
Forests:
Beaverhead-Deerlodge National Forest
Districts:
Madison Ranger District
States:
Montana
Counties:
Madison
Legal Land Description:
T10S, R1W, Sec. 7 and T9S, R1W, Sec. 32
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kevin Suzuki
5 Forest Service Road
Ennis, MT 59729
406-682-4253
ksuzuki@fs.fed.us
Last Updated: 6/26/2013