Crook Camp Trail #4107 Construction Project
We propose to relocate and construct about a half mile of the trail in to replace three sections that do not meet Forest Service design standards.
Project Summary
Location Summary:
Upper Clark Fork Landscape, Backyard Butte Management Area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/19/2013 |
| Comment Period | 05/07/2013 |
| Decision | 06/2013 (Estimated) |
| Implementation | 07/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Butte Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Crook Camp Trail #4107 Construction Project
Decision Signed Date: 06/25/2013
Legal Notice Date: 06/27/2013
Forests:
Beaverhead-Deerlodge National Forest
Districts:
Butte Ranger District
States:
Montana
Counties:
Silver Bow
Legal Land Description:
T2N, R7W, Sec 33
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jocelyn Dodge
1820 Meadowlark
Butte, MT 59701
406-494-0246
jdodge@fs.fed.us