Vigilante Electric Cooperative Special Use Permit.
Vigilante Electric proposes to rebuild an existing 69kV overhead transmission line. The new overhead transmission line runs across approximately 4,224 feet of NFS lands in a 50 foot wide corridor.
Project Summary
Location Summary:
Lima Tendoy Landscape, Horse Prairie North Management Area along Montana State Highway 278 near Big Hole Pass.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/04/2021 |
Decision | 07/2021 (Estimated) |
Implementation | 07/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Beaverhead-Deerlodge National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Vigilante Electric Cooperative Special Use Permit.
Decision Signed Date: 07/26/2021
Forests:
Beaverhead-Deerlodge National Forest
Districts:
Dillon Ranger District
States:
Montana
Counties:
Beaverhead
Legal Land Description:
Section 8, T.6S., R.13W.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeff Ingalls
420 Barrett St.
Dillon, MT 59725-3572
406-683-3931
jeff.ingalls@usda.gov
Last Updated: 5/27/2022