Mid Rivers Telephone Cooperative Fiber Installation
Installation of fiber optic line in existing right-of-way (2.13 acres) and new proposed right-of-way (4.19 acres). Methods will include direct burial, with common plowing, trenching and boring construction techniques.
Project Summary
Location Summary:
Southeast of Ekalaka, MT in T. 1 N., R. 59 E., Sec. 19 and 20; and T. 2 S., R. 61 E., Sec. 4, 9, and 10.%u200B
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/2023 (Estimated) |
Decision | 04/2023 (Estimated) |
Implementation | 06/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sioux Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Developing Proposal
Forests:
Custer Gallatin National Forest
Districts:
Sioux Ranger District
States:
Montana
Counties:
Carter
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Donald Ulrich
Box 37, Main and First
Camp Crook, SD 57724
406-587-6723
Donald.Ulrich@usda.gov
Last Updated: 3/29/2023