NorthWestern Energy Jackrabbit - Big Sky 161 kV Transmission Line Upgrade
Proposal to upgrade the existing 69kV line to a 161 kV line
Project Summary
Location Summary:
Gallatin Canyon along Highway 191 between Four Corners and the Big Sky Meadow Village
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 06/08/2010 |
| DEIS NOA in Federal Register | 10/19/2012 |
| FEIS NOA in Federal Register | 03/29/2013 |
| Decision | 03/2013 (Estimated) |
| Implementation | 05/2013 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bozeman Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Northwestern Energy Jackrabbit - Big Sky 161 kv transmission line upgrade
Decision Signed Date: 03/29/2013
Legal Notice Date: 03/29/2013
Forests:
Custer Gallatin National Forest
Districts:
Bozeman Ranger District
States:
Montana
Counties:
Gallatin
Legal Land Description:
within Townships 4, 5, 6 South and Range 4 East
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Amy Waring
3710 Fallon St. Suite C
Bozeman, MT 59718
406-255-1451
alwaring@fs.fed.us
Last Updated: 7/9/2013