East Paradise Allotment Management Plan
This is to study six open grazing allotments and determine if reauthorization of grazing is warranted
Project Summary
Location Summary:
Yellowstone Ranger District, south of I-90 each of Hwy. 89 S. Grazing allotments: Suce Cr C&H, 6-Mile Cr S. C&H, Mill Creek C&H, Pine Cr C&H, Elbow C&H
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/10/2013 |
| Comment Period | 11/17/2020 |
| Objection Period Start | 05/12/2021 |
| Decision | 12/2021 (Estimated) |
| Implementation | 01/2022 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Grazing, Rescissions Act Of 1995
Lead Management Unit:
Yellowstone Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Grazing Management
Project Activity:
Grazing Allotment Management; Grazing Authorizations
Current Status:
Completed
Project Decision Information
East Paradise Allotment Management Plan
Decision Signed Date: 12/09/2021
(Constrained Due to Litigation)
Forests:
Custer Gallatin National Forest
Districts:
Yellowstone Ranger District
States:
Montana
Counties:
Park
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Chauntelle Rock
5242 Highway 89 South
Livingston, MT 59047
406-222-1892
chauntelle.rock@usda.gov
Last Updated: 12/9/2021