Project Telephone Fiber line installation
Project Telephone proposes to install fiber line both where an existing right-of-way(ROW) is authorized and in new ROW adjacent to Highway 419 near Nye, MT. New ROW would be total of 4,832' x 20'(2.2 acres). If approved, permit would be amended.
Project Summary
Location Summary:
Located south-west of Nye, MT along Highway 419 in T. 5 S., R. 15 E., Sections 21, 28, 29, and 32.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/10/2022 |
| Decision | 05/2022 (Estimated) |
| Implementation | 06/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Beartooth Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Project Telephone Fiber line installation
Decision Signed Date: 05/16/2022
Forests:
Custer Gallatin National Forest
Districts:
Beartooth Ranger District
States:
Montana
Counties:
Stillwater
Legal Land Description:
T. 5 S., R. 15 E., Sections 21, 28, 29, 32
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Adam McClory
6811 Highway 212 South
Red Lodge, MT 59068
208-301-8224
adam.mcclory@usda.gov
Last Updated: 5/24/2022