Nichols Creek Road Reconstruction Project
The primary purpose and need for the Nichols Creek Road Reconstruction Project is to address road conditions that are causing resource degradation. The project responds to direction provided in the Custer Gallatin National Land Management Plan (2020)
Project Summary
Location Summary:
he Nichols Creek Road (FS Road 2478) is located off the West Fork Road (FS Road 2071), approximately 3 miles west of Red Lodge, MT.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/29/2023 |
| Decision | 11/2023 (Estimated) |
| Implementation | 06/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Beartooth Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Current Status:
Completed
Project Decision Information
Nichols Creek Road Reconstruction Project
Decision Signed Date: 11/29/2023
Forests:
Custer Gallatin National Forest
Districts:
Beartooth Ranger District
States:
Montana
Counties:
Carbon
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Drew Grimes
6811 Highway 212 South
Red Lodge, MT 59068
406-446-4528
drew.grimes@usda.gov
Last Updated: 1/25/2024