Soda Creek Channel Restoration
0.5 miles of Soda Creek's channel below the crossing with Hwy 46 will be re-designed to create the proper sinuosity, width, and depth of the channel. Restoration work in 1997 following flood damage that created channel instabilty will be rectified.
Project Summary
Current Status:
Completed
Location Summary:
Township 18 South, Range 8 East, Southeast 1/4 Section 11.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/10/2012 |
| Comment Period | 04/13/2012 |
| Decision | 11/2012 (Estimated) |
| Implementation | 12/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (7), 36 Cfr 220.6(E)(7)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bend/Fort Rock Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Project Decision Information
Soda Creek Restoration
Decision Signed Date: 11/14/2012
Forests:
Deschutes National Forest
Districts:
Bend/Fort Rock Ranger District
States:
Oregon
Counties:
Deschutes
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Thomas Walker
63095 Deschutes Market Rd
Bend, OR 97701
541-383-4787
tawalker@fs.fed.us