Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/08/2006 |
| Comment Period | 09/12/2007 |
| Decision | 12/2007 (Estimated) |
| Implementation | 05/2008 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (7), 36 Cfr 220.6(E)(7)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Crescent Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management
Project Activity:
Watershed Improvements
Current Status:
Completed
Project Decision Information
2007 Spruce Creek Riparian Rehabilitation
Decision Signed Date: 12/13/2007
Forests:
Deschutes National Forest
Districts:
Crescent Ranger District
States:
Oregon
Counties:
Klamath
Legal Land Description:
T25S, R07E, Sections 34 and 35; T26S, R07E, Sections 2 and 3
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Paul Powers
136471 Hwy 97 North
Crescent, OR 97733
541-433-3236
ppowers@fs.fed.us
Last Updated: 12/28/2007