Installation of a Buried Electrical Line at Recreation Residence Tract F Lot 2
The project would bury a new electric line alongside of an exsiting driveway in semi-disturbed and compacted area.
Project Summary
Location Summary:
The proejct is located near Camp Sherman, Oregon in Tract F, Lot 2
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/12/2012 |
| Comment Period | 04/14/2012 |
| Decision | 05/2012 (Estimated) |
| Implementation | 07/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sisters Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Installation of buried electrical line Recreation Residence Tract F, Lot 2
Decision Signed Date: 05/17/2012
Legal Notice Date: 05/21/2012
Forests:
Deschutes National Forest
Districts:
Sisters Ranger District
States:
Oregon
Counties:
Jefferson
Legal Land Description:
T13S, R09E, section 10 W. M.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Michael Keown
Pine Street and Hwy. 20
Sisters, OR 97759
541-549-7706
slmoore@fs.fed.us
Last Updated: 6/25/2012