Bend Surface Water Improvement Project
The Forest proposes to issue a special use permit to the City of Bend to authorize the City to upgrade the existing Bridge Creek intake facility and replace the aging Bridge Creek water supply pipelines.
Project Summary
Location Summary:
West of Bend, Oregon between the City's water intake and outback reservior site. Pipeline route is primarily along FSR 4601 and 4603
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/18/2012 |
Comment Period | 04/10/2013 |
Objection Period Start | 07/26/2013 |
Decision | 11/2013 (Estimated) |
Implementation | 01/2014 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bend/Fort Rock Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
DN/FONSI Special Use Permit City of Bend Bridge Creek Water Supply System
Decision Signed Date: 11/04/2013
Forests:
Deschutes National Forest
Districts:
Bend/Fort Rock Ranger District
States:
Oregon
Counties:
Deschutes
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rod Bonacker
63095 Deschutes Market Rd
Bend, OR 97701
541-383-5554
bpeer@fs.fed.us
Last Updated: 1/2/2018