Midstate Finley Butte Road Project
Midstate is proposing to bury four 3inch conduits (3 for power lines and 1 for fiber) in its existing ROW paralleling Finley Butte Road to install current overhead lines underground.
Project Summary
Location Summary:
Along Finley Butte Road in La Pine, near the BPA Substation in Midstate's existing ROW
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/10/2014 |
| Decision | 06/2015 (Estimated) |
| Implementation | 07/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bend/Fort Rock Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Midstate Finley Butte Road Project DM
Decision Signed Date: 06/08/2015
Forests:
Deschutes National Forest
Districts:
Bend/Fort Rock Ranger District
States:
Oregon
Counties:
Deschutes
Legal Land Description:
T 22 S., R 11 E., Section 18 WM,
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lisa Dilley
63095 Deschutes Market Rd
Bend, OR 97701
541-383-4025
lldilley@fs.fed.us
Last Updated: 6/23/2015