Crescent Creek Wild and Scenic River Management Plan
In 1988, the US Congress designated Crescent Creek as a Wild and Scenic River (WSR). This is the proposed management plan associated with that designation. Plan will outline Outstanding Remarkable Values and how to maintain them into the future.
Project Summary
Location Summary:
WSR designation begins approximately at the Crescent Lake Dam and continues for ten river miles until approximately the Crescent Lake Campground.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/15/2015 |
| Comment Period | 07/12/2018 |
| Objection Period Start | 09/17/2019 |
| Decision | 11/2019 (Estimated) |
| Implementation | 01/2020 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Crescent Ranger District
Notice and Comment Regulation:
219 (2012)
Project Purpose:
Special Area Management
Project Activity:
Plan Amendment; Special Area Management
Current Status:
Completed
Project Decision Information
Crescent Creek Wild and Scenic River Management Plan
Decision Signed Date: 11/26/2019
Legal Notice Date: 12/04/2019
Forests:
Deschutes National Forest
Districts:
Crescent Ranger District
States:
Oregon
Counties:
Klamath
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kyle Wright
136471 Hwy 97 North
Crescent, OR 97733
541-433-3262
kylewright@fs.fed.us