2022 Midstate Electric Right-of-way Clearing
Midstate is requesting to mow/masticate/cut or trim unwanted vegetation on 9.5 miles within their right-of-way.
Project Summary
Location Summary:
Treatment Area 1 is from Midstate poles 71197 and 71321 to 71311 and 70190 (Mowich substation to Fre-Win boundary). Treatment Area 2 is from Midstate poles 16143 to 16177 (south of Crescent Creek)
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/20/2022 |
| Decision | 06/2022 (Estimated) |
| Implementation | 06/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Crescent Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
2022 Midstate Electric Right-of-way Clearing Treatment Area 1A
Decision Signed Date: 06/08/2022
Forests:
Deschutes National Forest
Districts:
Crescent Ranger District
States:
Oregon
Counties:
Klamath
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Meria Page
136471 Hwy 97 North
Crescent, OR 97733
541-433-3230
ina.page@usda.gov