East Tumbull Urban Interface Hazardous Fuels Reduction
Hazardous fuels reduction activities west of Tumalo, Bend, and Sunriver.
Project Summary
Location Summary:
Bend-Redmond
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/31/2005 |
| Objection Period Start | 07/21/2006 |
| Decision | 08/2006 (Estimated) |
| Implementation | 10/2006 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Hfra Title I: Wildland-Urban Interface
Lead Management Unit:
Bend/Fort Rock Ranger District
Notice and Comment Regulation:
218
Project Purpose:
Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Completed
Project Decision Information
East Tumbull Hazardous Fuels Reduction Project Environmental Assessment
Decision Signed Date: 08/25/2006
Forests:
Deschutes National Forest
Districts:
Bend/Fort Rock Ranger District
States:
Oregon
Counties:
Deschutes
Legal Land Description:
T18-19S R11E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jim Schlaich
63095 Deschutes Market Rd
Bend, OR 97701
541-383-4725
jschlaich@fs.fed.us
Last Updated: 6/6/2011