Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/30/2023 |
| Decision | 10/2023 (Estimated) |
| Implementation | 10/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bend/Fort Rock Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
NRCS Irish and Taylor SNOTEL Soil Sensor Installation
Decision Signed Date: 10/20/2023
Forests:
Deschutes National Forest
Districts:
Bend/Fort Rock Ranger District
States:
Oregon
Counties:
Deschutes
Legal Land Description:
Legal Location: Township 20 South, Range 6 East, Section 25, SE 1/4.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Meria Page
63095 Deschutes Market Rd
Bend, OR 97701
541-433-3230
ina.page@usda.gov
Last Updated: 10/20/2023