Buckhorn Access Project
Construct and reconstruct an access road to the proposed Buckhorn mine on private lands; approve occupancy for a water infiltration area and pipeline, water agmentation sites, fencing, utility lines, mitigation sites and water monitoring facilities.
Project Summary
Current Status:
Completed
Location Summary:
Buckhorn Mountain 3 miles east of Chesaw, Washington and access roads 3550, 3575, 3575-120
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 07/19/2006 |
| DEIS NOA in Federal Register | 08/28/2006 |
| FEIS NOA in Federal Register | 02/03/2007 |
| Decision | 01/2007 (Estimated) |
| Implementation | 03/2007 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tonasket Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
Buckhorn Access Project
Decision Signed Date: 01/17/2007
Legal Notice Date: 02/03/2007
Forests:
Okanogan-Wenatchee National Forest
Districts:
Tonasket Ranger District
States:
Washington
Counties:
Okanogan
Legal Land Description:
T39 & 40N, R30 & 31 E, WM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Phillip Christy
1 West Winesap
Tonasket, WA 98855
509-486-5137
pchristy@fs.fed.us
Last Updated: 3/28/2007