White Pass Ski Area - Chairlift 4 Replacement Project
White Pass proposes to replace the existing double chairlift with a new quad chairlift. The new lift would be installed in the same alignment as the current lift, with the same bottom and top terminal locations.
Project Summary
Location Summary:
Approximately 55 miles west of Yakima, WA and 20 miles east of Packwood, WA.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/08/2025 |
Decision | 03/2025 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Naches Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Facility Maintenance
Current Status:
In Progress
Forests:
Okanogan-Wenatchee National Forest
Districts:
Naches Ranger District
States:
Washington
Counties:
Lewis; Yakima
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kimberly Larned
10237 Highway 12
Naches, WA 98937
509-852-1062
kimberly.larned@usda.gov