Culvert Removal in an Unnamed Salmon River Tributary
Removal of a galvanized corrugated 2 feet wide x 12 feet long culvert from an unnamed creek that is a tributary of Crowley Creek in a decommissioned FS road. This culvert is corroded and is scouring the creek banks at both sides, up and down stream.
Project Summary
Location Summary:
Crowley Creek is a tributary of the Salmon River Estuary.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/01/2015 |
Decision | 07/2015 (Estimated) |
Implementation | 08/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hebo Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Current Status:
Completed
Project Decision Information
Unnamed Creek Culvert Removal Project Decision Memo
Decision Signed Date: 07/23/2015
Forests:
Siuslaw National Forest
Districts:
Hebo Ranger District
States:
Oregon
Counties:
Tillamook
Legal Land Description:
T6S R11W S13
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Adriana Morales
31525 Hwy 22
Hebo, OR 97122
503-392-5135
adrianammorales@fs.fed.us
Last Updated: 7/27/2015