Cedar Creek Project
The Project will analyze for approximately 12,101 acres of treatment to restore and maintain late seral forest conditions to support species that rely on those habitats and to improve the water quality of the project area and subwatersheds.
Project Summary
Location Summary:
The project is primarily within the Middle and Upper Steamboat Creek subwatersheds, approximately 40 miles east of Glide in Douglas County Oregon.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/2026 (Estimated) |
| Comment Period | 07/2026 (Estimated) |
| Objection Period Start | 09/2026 (Estimated) |
| Decision | 12/2026 (Estimated) |
| Implementation | 03/2027 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
North Umpqua Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products); Fuels Management; Watershed Management
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green)
Current Status:
Developing Proposal
Forests:
Umpqua National Forest
Districts:
North Umpqua Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kaitlin Tidwell
18782 North Umpqua Highway
Glide, OR 97443
541-496-4194
Kaitlin.Tidwell@usda.gov
Last Updated: 1/26/2026