Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/8/2025 |
| Decision | 6/2026 (Estimated) |
Expected Analysis Type:
Categorical Exclusion
Lead Management Unit:
Wakulla Ranger District
Project Purpose:
Fuels management; Vegetation management (other than forest products)
Current Status:
Developing Proposal
Project Decision Information
Expected Decision Date: 6/2026 (Estimated)
States:
Florida
Counties:
Leon