Hog Valley Scrub
Harvest about 3,425 ac. of crookedwood, and about 3,120 ac. of sand pine. Reforest about 3,350 ac. to early successional sand pine scrub. Convert and restore about 15 ac. of off-site sand pine to longleaf pine.
Project Summary
Location Summary:
Compartments: 1, 2, 3, 4, 6, 10, 11, 13, 15, 16, 17, 21, 22, 31, 32, 35, and 100.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/31/2009 |
Comment Period | 03/07/2011 |
Decision | 04/2011 (Estimated) |
Implementation | 06/2011 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lake George Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Fuels Management; Forest Products; Wildlife, Fish, Rare Plants
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Hog Valley Scrub
Decision Signed Date: 04/13/2011
Legal Notice Date: 04/18/2011
Forests:
National Forests In Florida
Districts:
Lake George Ranger District
States:
Florida
Counties:
Marion; Putnam
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Frank Brandt
17147 East Highway 40
Silver Springs, FL 3488-5849
352-625-2520, ext. 2507
fbrandt@fs.fed.us
Last Updated: 4/21/2011