Highway 40 Fiber Optic Utility Lines
Installation of Fiber Optic Line along Highway 40 within the existing ROW both on existing utility poles and underground (through side boring and minimal trenching) on the Ocala National Forest
Project Summary
Location Summary:
Extending the entire length of Highway 40 through the Ocala National Forest and sidespurs along County Roads and Hwy 19.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/22/2017 |
Decision | 07/2018 (Estimated) |
Implementation | 08/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lake George Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Highway 40 Fiber Optic Utility Lines
Decision Signed Date: 07/16/2018
Forests:
National Forests In Florida
Districts:
Lake George Ranger District
States:
Florida
Counties:
Lake; Marion
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Heather Ellison
17147 East Highway 40
Silver Springs, FL 3488-5849
352-625-2520 x2526
hellison@fs.fed.us
Last Updated: 8/31/2018