Proposed special use for Gulf Power Company transmission line
Gulf Power Company has applied for a special use permit to construct an electric transmission line on an existing utility right of way on the Apalachicola National Forest. Project information is available at www.NFRCEA.ene.com or upon request.
Project Summary
Location Summary:
The proposed transmission line would be co-located with the existing City of Tallahassee right of way for ~11mi in the northeastern part of the forest.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/09/2019 |
Comment Period | 09/02/2020 |
Objection Period Start | 10/11/2020 |
Decision | 12/2020 (Estimated) |
Implementation | 01/2021 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Wakulla Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Proposed special use for Gulf Power Company transmission line
Decision Signed Date: 12/07/2020
Forests:
National Forests In Florida
Districts:
Wakulla Ranger District
States:
Florida
Counties:
Leon
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Matthew Trager
57 Taff Drive
Crawfordville, FL 32327
850-523-8582
mdtrager@fs.fed.us