Talquin Electric Utility Line Reconstruction
The proposal is to rebuild an existing 60 year old single-phase, 14.4 kV overhead electric distribution line attached to wooden poles for indefinite, year-round use. Approximately 3.5 miles of single-phase, 14.4 kV overhead electric distribution line
Project Summary
Location Summary:
Approximately 6.3 acres (3.5Miles
* 15 feet wide) of Right-Of-Way along Vilas Sumner
Rd. NFR 120
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/07/2023 |
| Decision | 12/2023 (Estimated) |
| Implementation | 12/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Apalachicola Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Talquin Electric Utility Line Reconstruction
Decision Signed Date: 12/12/2023
Forests:
National Forests In Florida
Districts:
Apalachicola Ranger District
States:
Florida
Counties:
Liberty
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ruby Roberts
P.O. Box 579
Bristol, FL 32321
850-523-8539
ruby.roberts@usda.gov
Last Updated: 12/12/2023