Nicolet Waterways Restoration Project
This project would restore and improve rivers, streams, and creeks under a programatic waterway program for the Nicolet side of the forest.
Project Summary
Current Status:
Completed
Location Summary:
Nicolet National Forest
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/22/2012 |
| Comment Period | 12/22/2012 |
| Decision | 02/2013 (Estimated) |
| Implementation | 04/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (7), 36 Cfr 220.6(E)(7)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lakewood-Laona Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Watershed Improvements
Project Decision Information
Nicolet Waterways Restoration Project
Decision Signed Date: 02/24/2013
Forests:
Chequamegon / Nicolet National Forest
Districts:
Eagle River-Florence Ranger District; Lakewood-Laona Ranger District
States:
Wisconsin
Counties:
Florence; Forest; Langlade; Oconto; Oneida; Vilas
Legal Land Description:
Lakewood-Laona and Eagle River-Florence Ranger Districts
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Scott Anderson
15085 State Road 32
Lakewood, WI 54138
715-674-4481
scottanderson@fs.fed.us
Last Updated: 2/26/2013