Chequamegon Communication Cooperative, Inc. Permit Reissue
Proposal is to reauthorize the existing facilities; issuing a new Communications Use Lease for a new term. Existing facility includes a tower, several structures in a fenced area, and access road. This proposal does not involve new construction.
Project Summary
Current Status:
Completed
Location Summary:
The proposed project area is west of the community of Ino in Bayfield County Wisconsin
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/29/2013 |
| Comment Period | 11/29/2013 |
| Decision | 02/2014 (Estimated) |
| Implementation | 03/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Washburn Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Chequamegon Communication Cooperative, Inc. Permit Re-Issue
Decision Signed Date: 02/10/2014
Legal Notice Date: 02/15/2014
Forests:
Chequamegon / Nicolet National Forest
Districts:
Washburn Ranger District
States:
Wisconsin
Counties:
Bayfield
Legal Land Description:
T47N R7W Sec 29, Bayfield County, WI
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jonathan McNeill
113 Bayfield St. East
Washburn, WI 54891
715-762-5154
jdmcneill@fs.fed.us
Last Updated: 2/27/2014