Townsend Project
Vegetation and Road Management Project (to access click on "Analysis" for the Draft EIS). If you are having trouble viewing these documents in Internet Explorer please try a different web browser such as Chrome, FireFox or other web browser.
Project Summary
Current Status:
Completed
Location Summary:
Northeast Langlade, Northwest Oconto and South Forest Counties
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 05/29/2015 |
| DEIS NOA in Federal Register | 12/30/2017 |
| FEIS NOA in Federal Register | 03/29/2018 |
| Objection Period Start | 04/01/2018 |
| Decision | 08/2018 (Estimated) |
| Implementation | 08/2018 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lakewood-Laona Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Forest Products
Project Activity:
Timber Sales (Green)
Project Decision Information
Townsend Project
Decision Signed Date: 08/21/2018
Forests:
Chequamegon / Nicolet National Forest
Districts:
Lakewood-Laona Ranger District
States:
Wisconsin
Counties:
Forest; Langlade; Oconto
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
John Lampereur
15085 State Road 32
Lakewood, WI 54138
715-276-6333
jlampereur@fs.fed.us
Last Updated: 8/21/2018