Bayfield Electric SUP 2018
To replace about 3,000 ft of existing overhead powerline with a new underground line within the existing utility corridor. New buried cable would be within the existing right-of-way. Proposal includes the removal of overhead supporting infrastructure
Project Summary
Current Status:
Completed
Location Summary:
Near Marengo Lake Road (FR 384), Town of Grandview, the section runs between FR 202 and FR 384.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/16/2018 |
| Decision | 08/2018 (Estimated) |
| Implementation | 08/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Great Divide Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Bayfield Electric SUP 2018
Decision Signed Date: 08/20/2018
Forests:
Chequamegon / Nicolet National Forest
Districts:
Great Divide Ranger District
States:
Wisconsin
Counties:
Bayfield
Legal Land Description:
T 44 North, R 5 West, Sec 4, Bayfield County, WI
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jonathan McNeill
10650 Nyman Avenue
Hayward, WI 54843
(715) 762-5154
jdmcneill@fs.fed.us
Last Updated: 8/28/2018