2019 Bayfield Electric Pigeon Lake Line Burial
An amendment to the Special Use Permit to relocate an existing powerline that is being affected by high water in Pigeon Lake with a new underground line along FR228. Proposal includes the removal of old infrastructure.
Project Summary
Current Status:
Completed
Location Summary:
Bayfield County T45N, R8W, Sections 26 and 35
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/22/2019 |
| Decision | 07/2019 (Estimated) |
| Implementation | 08/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Washburn Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Bayfield Electric Pigeon Lake Line Burial 2019
Decision Signed Date: 07/31/2019
Forests:
Chequamegon / Nicolet National Forest
Districts:
Washburn Ranger District
States:
Wisconsin
Counties:
Bayfield
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jennifer Maziasz
113 Bayfield St. East
Washburn, WI 54891
715-373-2667 ext. 5235
jennifer.maziasz@usda.gov
Last Updated: 12/10/2019