Clark Electric New Line Install and Removal
Clark Electric Cooperative proposes to install approximately 680 feet of 7.2 KV buried cable inside conduit. Clark Electric Cooperative also proposes to remove 2,700 feet (7.2KV) overhead line within a 40 foot wide ROW located west of highway ROW.
Project Summary
Current Status:
Completed
Location Summary:
Project is located in Taylor County in the Town of Grover (T32N, R2W, Sec 33) along County Highway M
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/18/2020 |
| Decision | 10/2020 (Estimated) |
| Implementation | 10/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Medford-Park Falls Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Clark Electric New Line Install and Removal
Decision Signed Date: 10/22/2020
Forests:
Chequamegon / Nicolet National Forest
Districts:
Medford-Park Falls Ranger District
States:
Wisconsin
Counties:
Taylor
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kelly Scarbrough
850 North 8th, Hwy 13
Medford, WI 54541
715-362-1314
Kelly.Scarbrough@usda.gov