2022 WPS Forest County T
Special Use Permit for installation of new underground electrical facilities. Replacement of existing overhead line to underground along north side of County Highway T between Blackwell Junction Road and Nicolet State Trail.
Project Summary
Current Status:
Completed
Location Summary:
Lakewood-Laona Ranger District, Forest County, T35 N, R15E, Section 18
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/08/2022 |
| Decision | 01/2023 (Estimated) |
| Implementation | 01/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chequamegon / Nicolet National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
2022 WPS Forest County T
Decision Signed Date: 01/31/2023
Forests:
Chequamegon / Nicolet National Forest
Districts:
Lakewood-Laona Ranger District
States:
Wisconsin
Counties:
Forest
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Brady Howe
500 Hanson Lake Road
Rhinelander, WI 54501
715-362-1300
brady.howe@usda.gov