Northern Natural Gas Pipeline Maintenance Dig Long Lake Road
Inline inspection indicated that four sites needed inspection and possible repair. The existing pipeline will be excavated for visual inspection and necessary repairs.
Project Summary
Current Status:
Completed
Location Summary:
Near Long Lake Road in northern Great Divide Ranger District
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/17/2025 |
| Decision | 08/2025 (Estimated) |
| Implementation | 08/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chequamegon / Nicolet National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Northern Natural Gas Pipeline Maintenance Dig Long Lake Road
Decision Signed Date: 08/22/2025
Forests:
Chequamegon / Nicolet National Forest
Districts:
Great Divide Ranger District
States:
Wisconsin
Counties:
Ashland
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Casey Swanson
500 Hanson Lake Road
Rhinelander, WI 54501
715-889-4917
casey.swanson@usda.gov
Last Updated: 8/26/2025