Day Lake Dam Repairs
Day Lake Dam needs repairs. The repairs will require a drawdown of the lake. While the lake is drawn down other previously analyzed projects and habitat improvement projects will be implemented.
Project Summary
Current Status:
Completed
Location Summary:
Day Lake north of Clam Lake, Wisconsin
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/15/2025 |
| Comment Period | 08/15/2025 |
| Decision | 11/2025 (Estimated) |
| Implementation | 07/2026 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (3), 36 Cfr 220.6(D)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Great Divide Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Developed Site Management; Facility Maintenance
Project Decision Information
Day Lake Dam Repairs
Decision Signed Date: 11/12/2025
Forests:
Chequamegon / Nicolet National Forest
Districts:
Great Divide Ranger District
States:
Wisconsin
Counties:
Ashland
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tyler LeMahieu
10650 Nyman Avenue
Hayward, WI 54843
715-362-1300 x1325
tyler.lemahieu@usda.gov
Last Updated: 12/2/2025