Hat Creek-Westwood PG&E Powerline Clearance

Project would remove hazardous fuels on the PG&E Hat Creek#1-Westwood 60kV Powerline. Vegetation would be cleared 40 ft out from centerline on both sides of the line and thinned 160 ft beyond that. Total width 400 ft, total length approx. 42 miles.

Location Summary

Project would occur along the PG&E powerline approx. 6 miles S/SW of Fall River Mills continuing for 42 miles to 5 miles N/NE of Westwood, CA. The project footprint is in Shasta and Lassen Counties.

Districts: Hat Creek Ranger District, Eagle Lake Ranger District

Project Milestones

MilestoneDate
Scoping Start12/15/2023
Comment PeriodN/A
Objection Period StartN/A
Decision05/01/2024 (Estimated)
Implementation06/01/2024 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public

https://www.fs.usda.gov/project/lassen/?project=64922